Accra-Kumasi Expressway: GAF completes 175.6km right-of-way clearance , hands over to gov’t
The Ghana Armed Forces (GAF) has completed the clearing of the Right-of-Way for the Accra-Kumasi Expressway and formally handed over the cleared corridor to the Government of Ghana.
The achievement marks a major step towards the construction of the planned 198.7-kilometre, six-lane expressway, which is expected to improve connectivity between Ghana’s two largest cities.
The Engineers Regiment of the Ghana Armed Forces cleared 175.6 kilometres of the project corridor, stretching from Ablekuma in the Greater Accra Region to Sewua in the Ashanti Region.
The exercise, which involved difficult terrain, forests, rivers and streams, was completed in 19 weeks—one week ahead of the 20-week deadline set by President John Dramani Mahama.
President Mahama received the handover on Monday, September 14, 2026, at Kwaso near Ejisu in the Ashanti Region.
He praised the military engineers for completing what he described as a demanding national assignment ahead of schedule.
“Within 19 weeks, 175.6 kilometres of road passing through virgin forests, crossing rivers and streams, our Ghana Armed Forces can today announce to all of us, as they say in military jargon, mission accomplished,” the President said.
GAF to support construction
Following the successful completion of the Right-of-Way clearance, President Mahama said the Engineers Regiment would be given a further role in the actual construction of the expressway.
He directed the Minister of Roads and Highways to incorporate the Engineers Regiment as a major subcontractor to the main contractor for the project.
President Mahama said the decision was justified by the military’s expertise and its successful mobilisation for the preparatory works.
He also tasked the Armed Forces with clearing the Right-of-Way for the proposed Greater Accra Orbital Road.
The military is further expected to assist with the installation of steel bridges at locations across the country.
“I’ve asked the Minister of Roads and Highways to identify all the sites that need steel bridges, and I’ve asked him to involve the Ghana Armed Forces to install these steel bridges across the length and breadth of this country,” President Mahama said.
National honour for Engineers Regiment
President Mahama announced that the Engineers Regiment would be recognised for its achievement at the next National Honours ceremony.
He said the ceremony, which is expected to form part of activities marking Ghana’s 70th anniversary of independence, would see the Engineers Regiment receive the Order of the Companion of the Volta.
The President said the honour was intended to reflect the nation’s appreciation for the military’s contribution to the project.
He also expressed confidence in the capacity of the Ghana Armed Forces to contribute to Ghana’s infrastructure development.
“The Ghana Armed Forces are capable and I have absolute trust in their ability to help this country in its infrastructure development,” he said.
Construction expected before Christmas
With the Right-of-Way now cleared, President Mahama said the government expects construction of the expressway to commence before Christmas 2026.
The government has already opened the process for selecting a contractor through an Expression of Interest, with pre-qualification and contractor selection expected to follow.
The President also announced that US$2 billion had been set aside to finance the project, with the funds held in a special account at the Bank of Ghana.
He said the funding would ensure that payment would not become a constraint once construction begins.
The completed expressway is expected to reduce travel time between Accra and Kumasi significantly, with President Mahama projecting that motorists could make the journey in about two hours at an average speed of 100 kilometres per hour.
The project will include eight interchanges, four rest stops, tow trucks and CCTV cameras, forming part of the government’s broader vision to develop modern transport corridors across Ghana.
General News
GTA Regional Directors Raise Concerns Over CEO Maame Efua Houadjeto’s Leadership
Fourteen Regional Directors of the Ghana Tourism Authority (GTA) have raised concerns about the leadership approach of the Authority’s Chief Executive Officer, Maame Efua Houadjeto, during a meeting with the Board of Directors to address what they describe as persistent organisational challenges.
The meeting, held on Monday, October 12, 2026, at 3:00 p.m., was convened to discuss issues the Regional Directors say have remained unresolved since July 2026.
According to the Directors, the engagement was not intended to serve as an arbitration process but rather to obtain responses to questions and concerns they had previously raised.
During the meeting, the Directors expressed their displeasure with the CEO’s leadership approach, highlighting concerns about stakeholder engagement, regional coordination and other issues they believe are affecting the effective operation of the Authority.
They indicated that the concerns extend beyond individual disagreements and touch on broader institutional matters that require attention to ensure the smooth functioning of the GTA.
The Directors maintained that their position was motivated by the need to safeguard the integrity of the institution and restore effective operations across its regional structures.
They also called on the Board of Directors to facilitate a formal response from the Office of the CEO to the issues raised, stressing the need for the concerns to be addressed through the appropriate institutional channels.
The engagement provided an opportunity for the Regional Directors to formally communicate their grievances to the Board and seek its intervention in resolving the outstanding matters.
The meeting ended with a call for further intervention by the Board of Directors to ensure that the issues raised receive the necessary attention and responses.
It remains unclear what specific questions have been pending since July, what responses the Regional Directors expect from the CEO, or what steps the Board intends to take following the meeting.
The outcome of any subsequent engagement between the Board, the CEO and the Regional Directors is expected to be important in determining how the concerns will be addressed and how coordination within the Authority will be strengthened.
General News
Gamal Gorkeh Nkrumah, Son of Ghana’s First President, Dies in Cairo
Gamal Gorkeh Nkrumah, son of Ghana’s founding President, Osagyefo Dr Kwame Nkrumah, has died in Cairo, Egypt, following a prolonged illness.
The Nkrumah family announced his death in a statement posted on the Facebook page of Samia Nkrumah, daughter of Ghana’s first president.
According to the statement, Gamal passed away peacefully in Cairo, where he had been receiving care at a rehabilitation centre after suffering a stroke.
The family described him as a beloved son, respected journalist, writer and intellectual who dedicated much of his life to examining the political, social and cultural developments shaping Africa and the wider world.
It said Gamal remained deeply committed to the ideals of justice, human dignity, African unity and international solidarity throughout his life.
As a journalist and commentator, he used his voice and intellect to analyse issues affecting Africa and the international community, earning recognition among friends, colleagues and readers who valued his insights and perspectives.
The family further described him as a man of profound intellectual curiosity, independent thought and quiet conviction, noting that he carried forward his father’s legacy in his own distinctive way while building a reputation based on his personal principles and achievements.
His death, the family said, represents a significant loss not only to his relatives and loved ones but also to the wider community of people who appreciated his work, humanity and engagement with important issues of his time.
The statement added that the family remembers Gamal with immense love, gratitude and pride, describing his wisdom, kindness and commitment to his values as an enduring source of inspiration.
The Nkrumah family also expressed appreciation to those who supported Gamal throughout his illness, particularly the medical professionals and caregivers in Cairo who provided him with treatment and care.
It extended its gratitude to the governments and people of both Egypt and Ghana for their support during the difficult period.
The family has appealed to the public to respect its privacy as it mourns the loss.
Details of memorial arrangements and opportunities for the public to pay tribute to Gamal Gorkeh Nkrumah’s life and legacy, according to the statement, will be communicated in due course.
General News
FOUR PROFESSORS SUE TO HALT GIMPA RECTOR SEARCH PROCESS AMID CONTROVERSY
Four professors at the Ghana Institute of Management and Public Administration (GIMPA) have filed a lawsuit seeking to halt aspects of the process to select a search committee for the appointment of a new Rector, escalating tensions over the institution’s leadership transition.
The plaintiffs are Professors Lord Mawuko Yevugah, Wisdom Akpalu, Kwami Adanu and Patrick Tandoh-Offin. They filed the action on October 5, 2026, challenging aspects of the process involving the Chairman of GIMPA’s Governing Council, the Institute’s Secretary and the Rector.
At the centre of the dispute is the Convocation register used to determine who could vote for representatives on the Rector Search Committee. The professors contend that about 30 newly appointed or promoted lecturers were included on the register despite questions over whether their appointments had received the necessary approval from the Governing Council.
They argue that allowing the lecturers to participate in the election could undermine the legitimacy of the process and have asked the court to ensure that the selection of the search committee complies with GIMPA’s 2020 Statutes. They also want the committee’s composition and the respective roles of the Governing Council and Convocation clarified.
GIMPA management, however, has indicated that a special ad hoc committee audited the Convocation register and confirmed that those listed had valid appointments, based on Human Resource Management records. Exceptions reportedly applied to staff on leave of absence or secondment.
The Convocation election proceeded on October 6. According to reports, Professor Patrick Tandoh-Offin contested to represent the professorial class but lost to Professor Emmanuel Gyamfi Numapau, who received 118 votes against Tandoh-Offin’s 35.
The legal challenge comes as GIMPA prepares for the end of Rector Professor Samuel Kwaku Bonsu’s tenure in August 2027. The Institute’s statutes require the search process to begin ahead of the incumbent’s departure.
The case raises questions about voting eligibility, institutional governance and the procedures for selecting the next Rector. The court’s determination could affect the process, although the available reports do not establish that an injunction has been granted or that the election
General News
EPA ORDERS IMMEDIATE HALT TO UNAPPROVED RECLAMATION WORKS NATIONWIDE — GOVERNMENT AGENCIES, CONTRACTORS ON NOTICE
The Environmental Protection Authority (EPA) has ordered an immediate halt to all land reclamation, mine-site rehabilitation, dredging and water-body restoration activities being undertaken without the requisite environmental permits across Ghana.
In a public notice issued on Wednesday, October 14, 2026, the Authority warned that institutions, companies, contractors and individuals operating without its approval must cease work immediately and report to the nearest EPA regional office or its head office for regulatory assessment.
The directive applies to both public and private projects, including government-sponsored, privately funded and donor-supported initiatives. The EPA specifically mentioned the Ministry of Lands and Natural Resources, Forestry Commission, Ghana Gold Board (GoldBod), Minerals Commission and Mineral Development Fund among the institutions required to ensure compliance.
Under Regulation 40 of the Environmental Protection (Environmental Assessment) Regulations, 2025 (L.I. 2504), reclamation and restoration activities fall within Ghana’s environmental assessment and permitting framework.
The covered activities include rehabilitating abandoned mining sites, backfilling excavated areas, restoring degraded land, revegetation, dredging and desilting rivers, modifying river channels and restoring polluted water bodies, wetlands and aquatic ecosystems.
The Authority stressed that securing a contract, obtaining funding approval, holding a mining lease or receiving authorisation from another public institution does not replace an EPA Environmental Permit. Similarly, consent from traditional authorities, memoranda of understanding and participation in government programmes cannot substitute for the required approval.
Contracting institutions have also been directed to verify the environmental permit status of projects before allowing contractors to mobilise to their sites.
The EPA acknowledged the importance of restoring lands and water bodies damaged by illegal and irresponsible mining but cautioned that rehabilitation efforts must not create further environmental destruction by bypassing regulatory safeguards.
It warned that individuals and institutions that continue unapproved operations after the notice would face action in accordance with applicable Ghanaian laws.
The directive reinforces the Authority’s position that environmental restoration, regardless of its funding source or purpose, must comply with the country’s permitting requirements.
General News
North Korea and China Open Long-Delayed Bridge
The opening of the long-awaited New Yalu River Bridge marks a significant step towards strengthening cross-border transport and trade between China and North Korea.
China and North Korea have officially opened a major bridge linking the two countries, ending a 12-year delay that kept the infrastructure project unused despite its completion in 2014.
The New Yalu River Bridge connects the Chinese border city of Dandong, in Liaoning province, with Sinuiju in North Korea. The four-lane crossing stretches approximately three kilometres across the Yalu River and is expected to improve the movement of goods between the neighbouring countries.
The project was originally intended to begin operating in 2014. However, the opening was postponed for years as infrastructure on the North Korean side, including connecting roads and customs facilities, remained incomplete. Analysts have also pointed to strained bilateral relations and disagreements surrounding economic cooperation as possible contributing factors.
Trade and economic implications
The new crossing is expected to ease pressure on the older China–North Korea Friendship Bridge, which has served as a major route for official trade between the two countries.
By providing additional road capacity, the new bridge could improve freight transportation, reduce congestion and support the movement of essential goods. Its strategic location is particularly important because China remains North Korea’s principal trading partner.
Nevertheless, the opening does not automatically guarantee a rapid increase in trade. International sanctions imposed in response to North Korea’s nuclear and weapons programmes continue to constrain economic activity, while the scale of future commercial traffic will depend on border arrangements and the two governments’ economic policies.
A signal of closer bilateral engagement
The bridge’s inauguration comes amid renewed diplomatic engagement between Beijing and Pyongyang. It also highlights China’s continued economic importance to North Korea as the latter seeks to maintain relationships with key regional partners.
For China, improved transport links could facilitate cross-border commerce and support economic activity in Dandong. For North Korea, the bridge offers additional capacity for importing goods and developing commercial infrastructure around Sinuiju.
However, the project’s long delay illustrates how political disagreements and economic considerations can obstruct infrastructure intended to improve regional connectivity.
What happens next?
Attention will now turn to how quickly the bridge becomes an established route for commercial traffic and whether the additional capacity translates into measurable growth in bilateral trade.
While the opening represents an important infrastructure milestone, its longer-term economic and diplomatic impact will depend on the willingness of both governments to sustain cooperation and the restrictions governing North Korea’s international trade.
The opening ends a lengthy wait for the two countries, but the bridge’s ultimate significance will be measured by the trade and cooperation it enables in the years ahead.
-
General News1 week agoWorld Cup Visa Storm: Kojo’s GTA Questions Resurface as Minority Demands Action
-
General News2 weeks agoSSNIT Unveils Big Plans to Transform Labadi, La Palm Beachfront into Tourism Hub
-
General News1 week agoPolitical communicators must prepare before speaking on teachers’ strike – Seth Afum Dankwah
-
Education2 weeks agoShould Schools Teach Students How to Handle Failure?
-
General News2 weeks agoUniversity of Ghana Announces Major Update on 2026/2027 Registration and Accommodation
-
General News2 weeks agoPolice Investigate Death of Three Children at Kobilmahigu; IGP Deploys Special Team
-
General News1 week agoUS Defense Department Cuts Ties With Anthropic Over AI Restrictions
-
Politics1 week agoGeorge Krobea Asante Alleges Deliberate Delay in Voting Process